Houston · Cypress · Katy · Memorial
Commercial · Average scoped to the gc schedule — typical 60–120k sq ft in 4–10 weeks

New Commercial Warehouses

Service entrance through high-bay LED, dock leveler power, and office build-out. One foreman from the pad to the final inspection.

About this service

New Commercial Warehouses for Houston Area Buildings

New warehouse construction lives or dies on two things — the electrical being on the GC schedule, and the high-bay lighting being right the first time. Solivance Electric handles the complete electrical scope for new tilt-wall and metal-building warehouse construction across Greater Houston: service-entrance sizing, main switchgear selection and bus setup, feeder distribution to distribution panels, high-bay LED layout with daylight-harvesting controls, dock leveler and overhead-door power, office-fit-out rough-in and trim, data and fire-alarm coordination with the other trades, and the final inspection walk. One foreman from ground-breaking to the final inspection — not a new face every week.

Service entrance through high-bay LED, dock leveler power, and office build-out. One foreman from the pad to the final inspection.

What's included

  • Design-build electrical for tilt-wall and metal-building warehouses
  • Service entrance, switchgear, and feeder distribution
  • High-bay LED lighting with occupancy and daylight controls
  • Dock leveler power, office fit-out, data and fire-alarm coordination
Google review
I definitely recommend Solivance Electric to anyone looking for a great, honest electrician. I cannot say enough good things about this company. After being without power for two days after Hurricane Beryl, we reached out wanting a generator interlock installed. Solivance Electric came out that very same day — they had worked through the night to get to everyone else needing the same. They made it clear they were prioritizing homes with children and pets. Aside from the interlock, they found other issues in the panel that could have caused a fire. These are my go-to guys from here on.
Yeny V.

How it works

01
Design-build against GC drawings

Single-line diagram, panel schedule, load calcs, fixture count, high-bay layout. Stamped where required. Coordinated with MEP before a hole is dug.

02
Underground rough-in

Service entrance conduits, site lighting feeders, dock-door stubs, future-expansion conduit — all in before the slab goes down.

03
Gear + high-bay install

Main switchgear set. Feeders run to sub-panels. High-bay LED layout installed after the roof deck is on, with daylight sensors and occupancy zones programmed.

Pricing

Ground-up commercial warehouse electrical typically runs $6–$12 per square foot for the full scope including service entrance, distribution, high-bay LED, dock power, and office fit-out. A 60,000 sq ft tilt-wall warehouse falls in the $360,000–$720,000 range. Heavier industrial loads (food-processing, cold-storage compressors, manufacturing machinery) push higher. Final pricing is a design-build conversation against the GC drawings.

Timeline

Typical 60–120k sq ft warehouse takes 4–10 weeks of on-site electrical, sequenced against the GC schedule — underground rough-in, service entrance, in-wall, tilt-wall-up electrical, high-bay layout after the deck is on, office build-out, dock and overhead-door power, trim, commissioning, final. We work the GC schedule, not our own.

Code & permits

Commercial warehouse electrical is designed under NEC Articles 200s (service and feeders) and 410 (lighting) with local amendments. High-bay LED layouts are photometric-designed to IES standards and often coordinated with an ASHRAE 90.1 energy review. Service-entrance equipment is selected for the AIC (available interrupting current) of the CenterPoint feeder at that address — not a guess from the spec sheet.

NEC 220/230NEC 410ASHRAE 90.1Harris County PermitsCenterPoint SCCR

Frequently Asked Questions

How much does new warehouse electrical cost?+
Ground-up commercial warehouse electrical typically runs $6–$12 per square foot for the full scope including service entrance, distribution, high-bay LED, dock power, and office fit-out. A 60,000 sq ft tilt-wall warehouse falls in the $360,000–$720,000 range. Heavier industrial loads (food-processing, cold-storage compressors, manufacturing machinery) push higher. Final pricing is a design-build conversation against the GC drawings.
How long does new warehouse electrical take?+
Typical 60–120k sq ft warehouse takes 4–10 weeks of on-site electrical, sequenced against the GC schedule — underground rough-in, service entrance, in-wall, tilt-wall-up electrical, high-bay layout after the deck is on, office build-out, dock and overhead-door power, trim, commissioning, final. We work the GC schedule, not our own.
Do you work directly with the GC or through an MEP?+
Both. We prefer to come in on design-build when the GC will let us, so we coordinate the electrical scope directly against the architectural and MEP drawings. On projects with a stamped MEP design already in place, we bid to spec and build to spec.
Do you handle the high-bay lighting design?+
Yes. Photometric layout, fixture count, wattage, color temperature, daylight-harvesting zones, and occupancy sensors. The lighting spec leaves the design desk as an IES file, not a fixture count.
Can you coordinate with the other subs — fire, data, HVAC?+
That is part of the job on a commercial warehouse. Fire-alarm tie-in with the fire sub, data cable pathways in the ceiling grid, roof-top unit disconnects and wiring with the mechanical sub, overhead-door controls with the door installer. The scheduling is as much of the work as the wiring.
Do you pull office fit-out inside the warehouse?+
Office rough-in and trim are in the standard scope. Multi-tenant office within a warehouse shell adds sub-metering and separate panels, which gets quoted as an additional line item.
Can you run future-expansion conduit in the underground?+
Always recommended. Future EV chargers, future high-bay additions, future exterior lighting, future equipment feeders — conduit is cheap to run with the trench already open. We stub it, cap it, and document it on the record drawings.
Who handles the utility coordination for the service entrance?+
We do. CenterPoint Energy service request, transformer sizing, primary service drop scheduling, meter coordination, and the final connection inspection are in our scope. The GC is not chasing the utility.

Ready to get started?

Free site walk. Fixed-fee quote in 24 hours. Permits pulled and inspections passed on the first walk.